Chronicle Solar Park Mauritius, Bambous

It took less than one year to build Mauritius’ first solar park. Up to 15.2 megawatts of solar power will be produced at this 34-hectare site and fed into the local grid.

 

Feb 2013

February 2013

Meeting with TAUBER SOLAR

Mar 2013

March 2013

Visit at TAUBER SOLAR in Tauberbischofsheim, Tauberbischofsheim, Germany / founding of Sarako

Apr 2013

April 2013

Planning / Measuring / Analysing

Aug 2013

August 2013

Start of construction of Mauritius’ first solar park

Oct 2013

October 2013

Excavation

Nov 2013

November 2013 in Germany

Technicians visit the TAUBER SOLAR GmbH Service Centre
Mauritians study solar park monitoring in Germany

November 2013 in Mauritius

Drilling and installation of the assembly system

Dec 2013

December 2013

Installation of the modules, laying cables, construction of the substation and connection facilities

Jan 2014

January 2014

Commissioning and testing

Feb 2014

February 2014

Connected to the grid on 18 February 2014